|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
![]() |
Foreword
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| a) ADB loan No | : | 2382 - BAN (SF). | |
| b) Project Title | : | Dhaka Water Supply Sector Dev’t Project (DWSSDP) | |
| c) Borrower | : | People's Republic of Bangladesh | |
| d) Executing Agency | : | Dhaka WASA | |
| e) Implementing Agency | : | Dhaka WASA | |
| f) Total estimated project cost | : | USD 212.70 million | |
| g) Financial planning | : | Is given in the matrix below |
Source |
Foreign Exchange |
Local Currency |
Total Cost |
Percent |
ADB |
35.4 |
114.60 |
150.00 |
70.5 |
GoB |
0 |
62.70 |
62.70 |
29.5 |
Total |
35.4 |
177.30 |
212.70 |
100.0 |
h) Status of project financing
| : | 10 December 2007 | ||
| : | 12 Dec 2007 | ||
| : | 14 Dec 2007 | ||
| : | 30 June2014 |
i) Date of last ADB review mission : 23 ~31 January, 2008
Part B
Utilization of Funds
During the period since loan effectiveness date, vis a vis the project’s being off the ground, quite a few contracts have been awarded. However, within the period, other significant and initial start-up works were taken up that included deployment of staff, setting up of a permanent office, organizing logistics/equipment from the existing base of DWASA, establishment of accounts and other related matters. Never the less, a sequential progress in respect of procurement inclusive of pertinent contracts and as well payment settled are shown below.
Sl No |
Name of the works |
RPA |
Total Settable amount (US$) |
1 |
Payment of staffs |
11,177.24 |
11,177.24 |
2 |
Procurement of 2 nr. vehicle |
70,869.12 |
90,666.27 |
3 |
Procurement of 2 nr. vehicle |
70,869.12 |
90,666.27 |
4 |
Procurement of 2 Nr. Pick-up |
49,354.04 |
66,773.12 |
5 |
Procurement of 2 Nr. Pick-up |
49,354.04 |
66,773.12 |
6 |
Procurement of Desktop , Laptop computer, Printer, UPS, Scanner and networking accessories |
19,761.94 |
19,761.94 |
7 |
Procurement of 4 nr. multifunction Photocopier |
13,354.62 |
13,354.62 |
8 |
Miscellaneous expenditure |
1,567.72 |
1,567.72 |
Total |
286,307.84 |
360,740.30 |
|
Cumulative contract awards financed by ADB loan
Number of contract awarded |
RPA |
Total Contract amount |
6* |
0.2863 |
0.3607 |
Cumulative disbursements from the ADB loan
Date |
Amount in million USD |
|
1.00 |
Part C
Project Purpose
The Project stands to contribute to sustainable provision and operation of urban water supply services in Dhaka city, by rehabilitating and strengthening the water supply system. Alongside it, there shall be a broad range of capacity building activities for DWASA to raise its management capacity to extend better services to its urban clientele.
The project Impact is sustained economic growth and public health improvement in Dhaka city.
The Outcomes of the project will be Provision and sustainable operations of improved water supply services in the project area. In addition, the expected outcome will also be to support GoB in achieving the reforms under the Program loan.
The project Output will entail rehabilitation and strengthening of the water supply system in the Dhaka city, and build the capacity of DWASA to optimize its system and provide improved services to the urban dwellers of Dhaka, stretching to the year 2025.
Part D
Specific Implementation Progress
As stated above, the progress under this report principally focuses the activities and development during the last quarter i.e. Mid-Dec’07 to Mid April’08 (in fact, somewhat in excess of 3 months). The following sections briefly narrate achievements todate on different areas of the project.
Targets and achievement of key work elements: Sequence of activities and milestones to be reached were specifically spelled out in the time frames provided in successive Aide Memoires that eventually led to the approval of the project by ADB Board, signing of the Loan agreement and importantly, declaration of the loan effectiveness. In effect, all the conditions for the 1st trench release (refer policy matrix of the RRP & PAM) were met on time, hence need not be narrated here.
The main stipulations and deadlines (agreed actions in matrix form) spelled out in the Aide Memoire of Jan’08 Inception Mission specified the following time-frame for some key activities.
Area/Issue(s) |
Agreed dates |
Actual status |
Procurement of consulting services |
|
|
DMC Pckg |
|
|
DWASA submitting RFP and S/L for DMC to ADB |
By 19 February, 2008 |
Done on 19 Feb 2008 |
ADB approving RFP and S/L for DMC |
By 4 March, 2008 |
Approval received on 14 Apr 2008 |
DWASA issuing RFP for DMC to bidders |
By 13 March, 2008 |
Issued on 17 Apr 2008 |
Receipt of Technical and Financial proposal |
|
Received on 24 June 2008 |
FCBC Pckg |
|
|
DWASA submitting RFP and S/L for FCBC to ADB |
By 2 March, 2008 |
Done on 17 Mar 2008 |
ADB approving RFP and S/L for FCBC |
By 16 March, 2008 |
Approval received on 5 May 2008 |
DWASA issuing RFP for FCBC to bidders |
By 25 March, 2008 |
Issued on 7 May 2008 |
Receipt of Technical and Financial proposal |
|
Received on 26 June 2008 |
PPMEC Pckg |
|
|
DWASA submitting RFP & S/L for PPMEC to ADB |
By 16 March, 2008 |
Done on 12 May 2008 |
ADB approving RFP and S/L for PPMEC |
By 30 March, 2008 |
Awaited |
DWASA issuing RFP for PPMEC to bidders |
By 8 April, 2008 |
Subject to above |
Approval of ADTA |
|
|
LGD sending TPP for ADTA to Planning Commission |
By 10 February, 2008 |
Done on 10 Feb 2008 |
Planning Commission holding SPEC meeting |
Two weeks after receiving the proposal (24 February, 2008) |
Done on 11 Mar 2008 |
Planning Commission approving TPP for ATDA |
Within two weeks after the SPEC meeting (9 March, 2008) |
Done on 27 Mar 2008 |
ERD signing the TA letter for ADTA |
Within a week after the SPEC meeting (2 March, 2008) |
Letter signed on 13 Apr 2008 |
Appointment of DPD-Finance |
|
|
DWASA submitting proposal to LGD |
By 2 February, 2008 |
Done on 02 Feb 2008 |
LGD issuing Government Order to form a selection committee |
By 10 February, 2008 |
12 March 2008 |
DPD-Finance being appointed |
By 15 March, 2008 |
Appointment letter issued |
Approval of pay scale for new organogram and recruitment |
|
|
LGD sending proposal to MOF |
By 6 February, 2008 |
|
MOF approving the proposal |
By 29 February, 2008 |
|
DWASA advertising newly-created posts |
Within a week after approval (6 Mar’08 |
Application received and scrutiny is in progress |
Others |
|
|
MOF and DWASA signing subsidiary loan agreement |
By 14 February, 2008 |
Yet to be done |
LGD holding IPSC meeting |
By 30 March, 2008 |
Meeting convened on 08 Apr 2008 |
Establishment and staffing
Consequent upon the loan becoming effective, a full fledged project office has been established at level nine of DWASA Bhaban. The Project Director (S. Qumarul Ahsan, an Addl. Chief Engineer) was in place even before the ‘loan-effective’ date.
Consistent with the precursor-requirements of the project, the following key personnel (apart from the PD) have been deployed under the project. They are:
Project Bank Account(s)
Requisite bank accounts for DWSSDP have already been established and are in operation
Progress of project component
While the matrix above containing agreed actions that stipulate specific actions on certain fronts and are reflective of the progress todate, the status of some important and significant work elements, somewhat in reiteration, are given below.
Recruitment of project Consultants
Selection of Design & Management Consultants (DMC):
Expected works in the next six months
Consistent with the overall work plan, there will be quite a few activities within the next quarter or so. They will include, among others:
1. Recruitment of Design and Management Consultants (DMC)
4. Getting all remaining PMU personnel recruited/deployed
5. Getting the Subsidiary Loan agreement (SLA) signed between DWASA & MoFin
6. Getting a grievance redressal mechanism appropriately designed and put in place
7. Mobilizing all three consultancy groups
8. Drawing Pragmatic work plan for the implementation of the physical part of the project elements that would essentially include: