GOVERNMENT OF THE PEOPLE’S REPUBLIC OF BANGLADESH
Local Government Division of MoLGRD&C
Dhaka Water Supply and Sewerage Authority (DWASA)

 

Progress Report

of

Dhaka Water Supply Sector Development Project (DWSSDP)
ADB Loan No. 2382 – BAN (SF)
Period: mid Dec’07- June’08

image

Project Management Unit (PMU)
Dhaka Water Supply Sector Development Project (DWSSDP)
DWASA Bhaban (8th Fl)
98 Kazi Nazrul Islam Avenue, Dhaka 1215

 

Table of Contents

Foreword

1

The Report

2

A. Introduction and Basic Data

2

B. Project Components

2

Progress Status

3

Part A: Basic Data

3

Part B: Utilization of Funds

4

Part C : Project Purpose

5

Part D : Specific Implementation Progress

  • Target and achievement of key work elements

5
5

  • Establishment and  staffing

6

  • Project Bank account

7

  • Progress of project component

7

      Recruitment of project Consultants

7

      Procurement of Office equipment / logistics

7

      Financial Progress

7

Expected works in the next six months

8

 

Foreword

Dhaka Water Supply Sector Development Project (DWSSDP) is relatively a recently launched development intervention. Consequent upon completion of a conceptualization-fact finding-appraisal process, the ADB-GoB loan agreement for the project was signed on and consequently, the Loan became effective on 14 December 2007. Since then, an Inception Mission visited Bangladesh between 23-31 January 2008. A set of actions and time-frame for them was agreed upon.

The project has juxtaposed and linked to it a set of program activities (to be carried out under the Program Loan component). The program as well has specific activities in the water supply and sanitation sector while a substantial part of it will embrace DWASA’s organizational and institutional development parameters. Broad responsibilities for the program activities, however, rest with LGD and MoFin, although there are substantial doables by DWASA as well.

In respect of the project, DWASA has attempted to carryout initial activities entailing staff deployment, setting up of office in physical terms, and importantly taking effective steps spanning the process of selection of project consultants (three packages). However, the relevant sections in the main body of this progress report, however brief, will give a wider reflection of the progress todate.

In the end, this is the first progress report that will be followed by many within the project period. Hence, as a starter, this report may have inadequacies, which we expect to be comprehensive in the future reports.

The Report

A. Introduction and Basic Data
Dhaka Water Supply Sector Development Program (DWSSDP) has been formulated in line with the GoB’s sector policies and strategies, particularly the Sector Development Program (SDP) for water supply and sanitation spectrum of the country. The SDP and related GoB policies set forth clear and well formulated development objectives, investment plans, institutional arrangements, and transition plans for the water supply and sanitation sector. ADB assistance for the ensuing project has been formulated on a ‘sector loan’ basis.

DWSSDP has two major components: the program loan and the project loan. The program loan encompasses principally reform measures to the water supply and sanitation sector, especially in the urban context. The remaining component of the loan mainly involves implementation of a water supply improvement project for Dhaka city that stands to be implemented by Dhaka WASA. This report shall principally focus on the project component.

B. Project Components
The project will have three (3) components as its principal output, which are summarized below:

a] Component A: Distribution System and Quality Improvement :

This component will involve physical rehabilitation and strengthening of DWASA’s water distribution network to minimize losses and to enable 24 hour pressurized water supply, and provision of water quality assurance and control measures, particularly within four out of six selected MODS zones. Its subcomponents are :

  • Distribution Network Rehabilitation and Strengthening
  • Water Quality and Monitoring System Improvement .
b] Component B: Capacity Building and Institutional Strengthening : This component will essentially include:
  • institutionalization of sound financial management, efficient billing, revenue collection and customer record systems
  • provision of comprehensive training for all levels of DWASA staff to optimize operational performance and upgrading of training facilities; and
  • extensive demand control and awareness campaign for consumers.
Pertinent sub-components are:
  • Financial Management Improvement
  • Training and Capacity Building
  • Demand Control and Public Awareness .
  • c] Component C: Project Management and Implementation Support : Its main subcomponents are:

     Consulting services entailing

      o project management and monitoring
      o detailed planning and design activities under the Project
      o contract structuring, tendering, execution, and management
      o construction supervision
      o preparation of a demand control, resource conservation and public awareness campaign, including the tariff awareness program; and
      o identification and development of various institutional strengthening measures, training modules and guidelines/manuals and provision of training.

    Consulting services will also include engagement of NGOs to manage parts of the demand control and community awareness program.

      Additionally, consulting services will be provided to assist DWASA in conducting a feasibility study for an optimal location of the future 500 mld SWTP.

    Now the brief delineation of project progress, largely given in tabular form, are as given below:

    Progress status
    Eversince DWSSDP has gone into implementation, there has been some notable progress todate. This particular progress report contains progress made on different fronts within the period of mid December to 30 June’08 period .

    Reiterating, the report essentially focuses on the project part (larger of the two major components) and it attempts to largely follow the format given in the PAM of the project

    Part A
    Introduction and Basic Data
    Narrated below are some of the basic data on the project particulars, given in a somewhat tabular form

      a) ADB loan No : 2382 - BAN (SF).
      b) Project Title : Dhaka Water Supply Sector Dev’t Project (DWSSDP)
      c) Borrower : People's Republic of Bangladesh
      d) Executing Agency : Dhaka WASA
      e) Implementing Agency : Dhaka WASA
      f) Total estimated project cost : USD 212.70 million
      g) Financial planning : Is given in the matrix below

    Source

    Foreign Exchange
    (US$)

    Local Currency
    (US$)

    Total Cost
    (US$)

    Percent

    ADB

    35.4

    114.60

    150.00

    70.5

    GoB

    0

    62.70

    62.70

    29.5

    Total

    35.4

    177.30

    212.70

    100.0

    h) Status of project financing

     
  • Dates of approval
  • : 10 December 2007
     
  • Loan agreement signing
  • : 12 Dec 2007
     
  • Loan effectiveness declaration
  • : 14 Dec 2007
     
  • Original ADB loan closing date
  • : 30 June2014

    i) Date of last ADB review mission        : 23 ~31 January, 2008

    Part B
    Utilization of Funds
    During the period since loan effectiveness date, vis a vis the project’s being off the ground, quite a few contracts have been awarded. However, within the period, other significant and initial start-up works were taken up that included deployment of staff, setting up of a permanent office, organizing logistics/equipment from the existing base of DWASA, establishment of accounts and other related matters. Never the less, a sequential progress in respect of procurement inclusive of pertinent contracts and as well payment settled are shown below.

    Sl No

    Name of the works

    RPA
     (US$)

    Total Settable amount (US$)

    1

    Payment of staffs

    11,177.24 

    11,177.24

    2

    Procurement of 2 nr. vehicle

    70,869.12

    90,666.27

    3

    Procurement of 2 nr. vehicle

    70,869.12

    90,666.27

    4

    Procurement of  2 Nr. Pick-up

    49,354.04

    66,773.12

    5

    Procurement of  2 Nr. Pick-up

    49,354.04

    66,773.12

    6

    Procurement of Desktop , Laptop computer, Printer, UPS, Scanner and networking accessories

    19,761.94

    19,761.94

    7

    Procurement of 4 nr. multifunction Photocopier

    13,354.62

    13,354.62

    8

    Miscellaneous expenditure

    1,567.72

    1,567.72

    Total

    286,307.84

    360,740.30

    [1 US$ = Taka 68.89, as per DPP rate]

    Cumulative contract awards financed by ADB loan

    Number of contract awarded

    RPA
    (million US$)

    Total Contract amount
    (million US$)

    6*

    0.2863

    0.3607

    *SL 2-7 in the table above

     

    Cumulative disbursements from the ADB loan

    Date

    Amount in million USD

     

    1.00

    As of now, no re-estimation of cost to completion felt necessary.


     

    Part C
    Project Purpose
    The Project stands to contribute to sustainable provision and operation of urban water supply services in Dhaka city, by rehabilitating and strengthening the water supply system. Alongside it, there shall be a broad range of capacity building activities for DWASA to raise its management capacity to extend better services to its urban clientele.

    The project Impact is sustained economic growth and public health improvement in Dhaka city.

    The Outcomes of the project will be Provision and sustainable operations of improved water supply services in the project area. In addition, the expected outcome will also be to support GoB in achieving the reforms under the Program loan.

    The project Output will entail rehabilitation and strengthening of the water supply system in the Dhaka city, and build the capacity of DWASA to optimize its system and provide improved services to the urban dwellers of Dhaka, stretching to the year 2025.

    Part D
    Specific Implementation Progress
    As stated above, the progress under this report principally focuses the activities and development during the last quarter i.e. Mid-Dec’07 to Mid April’08 (in fact, somewhat in excess of 3 months). The following sections briefly narrate achievements todate on different areas of the project.

    Targets and achievement of key work elements: Sequence of activities and milestones to be reached were specifically spelled out in the time frames provided in successive Aide Memoires that eventually led to the approval of the project by ADB Board, signing of the Loan agreement and importantly, declaration of the loan effectiveness. In effect, all the conditions for the 1st trench release (refer policy matrix of the RRP & PAM) were met on time, hence need not be narrated here.

    The main stipulations and deadlines (agreed actions in matrix form) spelled out in the Aide Memoire of Jan’08 Inception Mission specified the following time-frame for some key activities.

    Area/Issue(s)

    Agreed dates

    Actual status

    Procurement of consulting services

     

     

    DMC Pckg

     

     

    DWASA submitting RFP and S/L for DMC to ADB

    By 19 February, 2008

    Done    on 19 Feb 2008

    ADB approving RFP and S/L for DMC

    By 4 March, 2008

    Approval received on 14 Apr 2008

    DWASA issuing  RFP for DMC to bidders

    By 13 March, 2008

    Issued on 17 Apr 2008

    Receipt of Technical and Financial proposal

     

    Received on 24 June 2008

    FCBC Pckg

     

     

    DWASA submitting RFP and S/L for FCBC to ADB

    By 2 March, 2008

    Done  on 17 Mar 2008

    ADB approving RFP and S/L for FCBC

    By 16 March, 2008

    Approval received on 5 May 2008

    DWASA issuing  RFP for FCBC to bidders

    By 25 March, 2008

    Issued on 7 May 2008

    Receipt of Technical and Financial proposal

     

    Received on 26 June 2008

    PPMEC Pckg

     

     

    DWASA submitting RFP & S/L for PPMEC to ADB

    By 16 March, 2008

    Done on 12 May 2008

    ADB approving RFP and S/L for PPMEC

    By 30 March, 2008

    Awaited

    DWASA issuing  RFP for PPMEC to bidders

    By 8 April, 2008

    Subject to above

    Approval of ADTA

     

     

    LGD sending TPP for ADTA to Planning Commission

    By 10 February, 2008

    Done  on 10 Feb 2008

    Planning Commission holding SPEC meeting

    Two weeks after receiving the proposal (24 February, 2008)

    Done  on 11 Mar 2008

    Planning Commission approving TPP for ATDA

    Within two weeks after the SPEC meeting (9 March, 2008)

    Done on 27 Mar 2008

    ERD signing the TA letter for ADTA

    Within a week after the SPEC meeting (2 March, 2008)

    Letter signed on 13 Apr 2008

    Appointment of DPD-Finance

     

     

    DWASA submitting proposal to LGD

    By 2 February, 2008

    Done   on 02 Feb 2008

    LGD issuing Government Order to form a selection committee

    By 10 February, 2008

    12 March 2008

    DPD-Finance being appointed

    By 15 March, 2008

    Appointment letter issued

    Approval of pay scale for new organogram and recruitment

     

     

    LGD sending proposal to MOF

    By 6 February, 2008

     

    MOF approving the proposal

    By 29 February, 2008

     

    DWASA advertising newly-created posts

    Within a week after approval (6 Mar’08

    Application received and scrutiny is in progress

    Others

     

     

    MOF and DWASA signing subsidiary loan agreement

    By 14 February, 2008

    Yet to be done

    LGD holding IPSC meeting

    By 30 March, 2008

    Meeting convened on 08 Apr 2008

     

    Establishment and staffing
    Consequent upon the loan becoming effective, a full fledged project office has been established at level nine of DWASA Bhaban. The Project Director (S. Qumarul Ahsan, an Addl. Chief Engineer) was in place even before the ‘loan-effective’ date.

    Consistent with the precursor-requirements of the project, the following key personnel (apart from the PD) have been deployed under the project. They are:

    • Dy. Project Director (Tech -1) (Mohammad Shahjahan)
    • Dy. Project Director (Tech-2) (Kazi Abul Kashem)
    • Executive Engineers - 4 (four)

    DPD (Finance) has been appointed and expected to joint by 21 July 2008.
    In addition, support staffs have also been provided at the PMU.

    Apart from this, recruitment steps have been taken by the Admin division of DWASA for the staff that will be filled in through direct appointment. Recruitment of personnel for the 4 (four) PCUs is still to be done. The PMU has made it imperative to the management to effect recruitment of the PCU personnel (in accordance with the project organogram). Incidentally, recruitment process for the AEs and SAEs are in progress. Reportedly, the process will be completed within Sept’08.

    Project Bank Account(s)
    Requisite bank accounts for DWSSDP have already been established and are in operation

    Progress of project component
    While the matrix above containing agreed actions that stipulate specific actions on certain fronts and are reflective of the progress todate, the status of some important and significant work elements, somewhat in reiteration, are given below.

    Recruitment of project Consultants

     Selection of Design & Management Consultants (DMC):

    • EoI published: 13 November 2007
    • EoI received : 17 December 2007
    • Short listing & draft RFP sent to ADB: 19 February 2008
    • Endorsement of the draft RFP & shortlist by ADB: 14 April 2008
    • Issuance of RFP: 17 April 2008
    • Receipt of Technical and Financial proposal: 24 June 2008


    Selection of Financial & Capacity Building Consultants (FCBC):
    • EoI published: 26 November 2007
    • EoI received : 30 December 2007
    • Shortlisting & draft RFP sent to ADB: 17 March 2008
    • Endorsement of the draft RFP & shortlist by ADB: 5 May 2008
    • Issuance of RFP: 7 May 2008
    • Receipt of Technical and Financial proposal: 26 June 2008
    Selection of Project Performance Monitoring & Evaluation consultants (PPMEC):
    • EoI published: 14 January 2008
    • EoI received : 14 February 2008
    • Shortlisting & draft RFP sent to ADB: 12 May 2008
    • Endorsement of the draft RFP & shortlist by ADB: awaited
    • Issuance of RFP: subject to above

    Procurement of Office Eqp/logistics
    Procurement for office equipment (PCs, laptops, printers, scanners, UPS and others for networking) and project vehicles have already been done. Procurement process for project website design and development is already in an advanced stage.

    Financial Progress
    Up to the end of the reporting period, a total of US$ 1.0 million has been disbursed. Against this, corresponding expenditure made to this date stands at 0.2863 million.

     

    Expected works in the next six months
    Consistent with the overall work plan, there will be quite a few activities within the next quarter or so. They will include, among others:

    1. Recruitment of Design and Management Consultants (DMC)

    • Evaluation of the TP of DMC
    • Transmitting the evaluation of TPs of DMC to ADB, Manila for their approval
    • Consequent upon receipt of approval of TP, opening the FP and transmittal to ADB, Manila for final approval
    • Placing before CCGP for approval for the final selection of DMCs

    2. Recruitment of Financial & Capacity Building Consultants (FCBC)
    • Evaluation of the TP of FCBC
    • Transmitting the evaluation of TPs of FCBC to ADB, Manila for their approval
    • Consequent upon receipt of approval of TP, opening the FP and transmittal to ADB, Manila for final approval
    • Placing before CCGP for approval for the final selection of FCBCs
    3. Recruitment of Project Performance M&E Consultants (PPMEC)
    • Evaluation of the TP of PPMEC
    • Transmitting the evaluation of TPs of PPMEC to ADB, Manila for their approval
    • Consequent upon receipt of approval of TP, opening the FP and transmittal to ADB, Manila for final approval
    • Placing before CCGP for approval for the final selection of PPMECs

    4. Getting all remaining PMU personnel recruited/deployed

    5. Getting the Subsidiary Loan agreement (SLA) signed between DWASA & MoFin

    6. Getting a grievance redressal mechanism appropriately designed and put in place

    7. Mobilizing all three consultancy groups

    8. Drawing Pragmatic work plan for the implementation of the physical part of the project elements that would essentially include:

    • Survey
    • Design
    • Initiation of the Preparation of contract bids
    • Stocktaking of DWASA’s institutional and operational fronts by FCB consultants
    • Addressing the policy matrix requirements, especially those for which DWASA would be responsible for execution.
    On top of above, there shall be quite a few other activities that will come along the road to implementation of the project.